The A38 Stoke Road may shut all weekend, 8pm Friday 27 November to 6am Monday 30 November. Weeknight closures south of Oakalls follow from 30 November.

This is our weekly check of every live and proposed closure in the district, updated on Sunday 22 November 2026.

The A38 Stoke Road shuts again tonight, and may shut all next weekend. The county’s BREP page confirms closures between the Stoke Road/Charford Road junction and the Austin Road and Sherwood Road roundabout on two nights:

  • Saturday 21 November, 8pm to 6am on Sunday 22 November
  • Sunday 22 November, 8pm to 6am on Monday 23 November

A third closure is provisional, subject to confirmation: from 8pm on Friday 27 November to 6am on Monday 30 November, running continuously through the weekend, daytime included. The county says vehicles leaving Aldi can still do so using the current layout, and a signed pedestrian diversion is provided.

Weeknight closures on the A38 south of Oakalls follow from 30 November to 5 December. The BREP table now marks them “Planned”, which it defines as “traffic management permit granted”.

Primrose Hill at Headley Heath has been shut by flooding since 17 November. The county’s list of emergency closures has carried it since 11:15 that day, with no reopening date. Old Burcott Lane at Burcot is still shut after a sandstone rock cutting collapsed on 27 October, and Houndsfield Lane in Hollywood has been shut 24 hours a day since 16 November, for an anticipated 75 days.

Nothing is listed at M5 junctions 4 and 4a this week. National Highways’ 7-day report, running from Friday 20 to Thursday 26 November, has no closure there or on the M42 at junctions 1 to 3. It does list two single-night slip road closures at M5 junction 3, just over the district boundary at Frankley; see the motorway section below.

Everything below comes from the statutory closure orders, the National Highways closure report, the county council’s emergency closures list, the BREP programme page and National Rail’s engineering works list, all read on Sunday 22 November. Nothing is carried over on trust, and where we could not confirm something today we say so. The county’s newest notices for the district are those of 18 November in the Bromsgrove and Redditch Advertisers. National Rail’s engineering works list, read on 22 November, shows no works on the lines through Bromsgrove, Barnt Green or Redditch before Christmas; the Christmas closures at Birmingham New Street are set out below.

Closed right now

Road closures and restrictions in force in the Bromsgrove district, 22 November 2026
RoadExtentDatesReason
A38 Stoke Road, BromsgroveStoke Road/Charford Road junction to the Austin Road and Sherwood Road roundaboutNight of Sunday 22 November, 8pm to 6amCCTV survey of a Severn Trent main, BREP scheme B; signed diversion
Primrose Hill, Headley HeathNot statedListed since 11:15 on 17 November 2026, no end date givenFlooding, emergency closure
Houndsfield Lane, HollywoodAlcester Road to Hollywood Lane24 hours, 75 days from 16 NovemberGas main replacement, Cadent
Old Burcott Lane, BurcotNot statedListed since 12:15 on 27 October 2026, no end date givenLandslip, emergency closure
Dark Lane, RomsleySt Kenelms Road to Hillcrest Road24 hours, 26 October to 18 DecemberGas main replacement, Cadent
Hillcrest Road, Romsley167m north east from Dark Lane24 hours, 16 November to 4 DecemberGas main replacement, Cadent (phase 2)
The Strand, Bromsgrove (side road)Side road off The StrandListed since 25 January 2026, no end date givenCollapsing building, emergency closure
Warwick Avenue footway, BromsgroveLeft footway, 60m north from Stoke Road152 days, 24 hours, from 5 OctoberCarriageway and footway construction, BREP scheme D

Romsley’s seven-week gas main job is under way. Cadent’s closure runs 24 hours a day for an anticipated 54 days, in three phases:

  • Dark Lane, St Kenelms Road to Hillcrest Road: 26 October to 18 December, diverted via St Kenelms Road and Hillcrest Road
  • Hillcrest Road, 167 metres north east from Dark Lane: 16 November to 4 December
  • Poplar Lane and Dark Lane, Hillcrest Road to the B4551 Bromsgrove Road: 30 November to 11 December

The A38 Stoke Road diversion follows the A38 south to the A38/Kidderminster Road roundabout, then the A442 north to the A442/A450 roundabout, and comes back via the A450 and A448 to rejoin the A38 near the Oakalls roundabout, according to the county’s map description. The works are trial holes, CCTV surveys and drainage clearance, and the county says some may be noisy, particularly at the start of each shift. It says the notice was issued at short notice and apologises for the disruption.

Primrose Hill at Headley Heath appears on the county’s emergency list as “Primrose Hill Closed due to flooding”. The county gives no extent, diversion or reopening date for an emergency closure like this.

Old Burcott Lane at Burcot is shut by a landslip. The county’s list, read on 22 November, has carried “Old Burcott Lane Closed due to Landslip” since 12:15 on 27 October, with the engineer’s note that a sandstone rock cutting has collapsed. There is no diversion and no reopening date.

The oldest closure in Bromsgrove is not a roadworks job at all. A side road off The Strand has been listed as shut since 13:30 on 25 January 2026 because a building beside it is collapsing. It is still on the county’s list of emergency closures, read again on 22 November, as “The Strand, Side road bromsgrove closed due to collapsing building”, with no end date and no update.

Warwick Avenue loses its left footway for 60 metres north of Stoke Road for 152 days from 5 October. Pedestrians are signed along Warwick Avenue to Stoke Road via the bridge, then the A38 Stoke Road to Charford Road.

Finished since our last check

  • Charford Road, A38 junction to Lyttleton Avenue, the night closure from 20:00 on 19 November to 06:00 on 20 November
  • High Street, Church Road and St John Street, Bromsgrove, the 8am to 7pm closure for the lights switch-on on Saturday 21 November
  • Dayhouse Bank, Romsley, the one-day Openreach closure on 19 November (order made in the 18 November notice)
  • Brueton Avenue and Spadesbourne Road, the three-day dropped kerb closures from 16 November
  • the Alvechurch parking orders at Bear Hill and St Laurence Close, and the Old Station Road school keep clear order, which closed to objections on 18 November

Due to have ended, but not confirmed

The county publishes no reopening notices for these, so we cannot say they are open.

  • Old Birmingham Road, Alvechurch: 12 days from 9 November ran out about 20 November.
  • Blackwell Road, Barnt Green: five days from 16 November ran out about 20 November.
  • Barrow Hill Lane, Belbroughton: two days some time between 10 and 24 November; the county never said which.
  • Cobley Hill, Alvechurch: three days from 3 November ran out about 5 November.
  • Worcester Road and Hanover Street, Bromsgrove: nine days from 24 October ran out about 1 November.
  • The B4096 Old Birmingham Road at Marlbrook: Cadent’s 105 days from 21 July ran out about 3 November. The order allows up to 18 months if the work overruns.
  • The Stratford Road northern footway: the county expected it to reopen “by 9 October”. The BREP page still has not said that it did.

This week: to Sunday 29 November

Closures in and next to the Bromsgrove district from Sunday 22 to Sunday 29 November 2026
RoadWhenHours or lengthStatus
A38 Stoke Road, Charford Road junction to the Austin Road and Sherwood Road roundaboutNight starting Sunday 22 November8pm to 6amConfirmed on the BREP page; CCTV survey on a Severn Trent main
Whetty Lane, Rubery (St Chad's Road to Coppice Close)Monday 23 November1 dayOrder made; utility work, Severn Trent
Whitford Bridge Road, Stoke Prior (Moorgate Road to Woodgate Road)From Monday 23 November2 daysOrder made; remedial water works, Severn Trent
Curtis Close, Tutnall (B4184 Alcester Road to London Lane)Between 19 and 26 November2 daysOrder made; footway reconstruction, county council
Farley Lane, Romsley (Quantry Lane to the B4551 Bromsgrove Road)Between 20 November and 3 December3 daysOrder made; patching before surface dressing, county council
Orchard Crescent, Stoke PriorBetween 16 and 27 November1 dayOrder made; resurfacing, county council
Shaw Lane and Stoke Road, Stoke PriorBetween 17 and 30 November2 daysOrder made; patching, county council
Winwood Heath Road, Romsley (Shut Mill Lane to Farley Lane)Between 18 and 30 November2 daysOrder made; patching, county council
M5 northbound junction 3 entry slip, FrankleyNight starting Tuesday 24 November21:00 to 06:00National Highways maintenance; diversion via its network and local roads
M5 southbound junction 3 exit slip, FrankleyNight starting Wednesday 25 November21:00 to 06:00National Highways maintenance; diversion via its network and local roads
A38 Stoke Road, Aldi exit to the southFriday 27 November, 8pm, to Monday 30 November, 6amContinuous, day and nightProvisional, subject to confirmation; trial holes on a Severn Trent main, saw cutting and duct crossings, BREP schemes B and C

The weekend of 27 to 30 November is the one to plan around. The BREP news page calls it provisional and the works table marks it “Proposed/TBC”. If it goes ahead, the A38 Stoke Road between Charford Road and the Austin Road roundabout will be shut for 58 hours straight, daytime included. The works are trial holes and a condition check on a Severn Trent main, saw cutting, and duct crossings for new traffic signals and street lighting. The table holds 15 to 18 January 2027 as contingency dates for the same work.

Whetty Lane in Rubery is diverted via St Chad’s Road, New Road and Legion Road. Whitford Bridge Road is diverted via Woodgate Road and Moorgate Road. Curtis Close is diverted via the B4184 Alcester Road, Finstall Road, St Godwalds Road and Dusthouse Lane, and Farley Lane via Quantry Lane and the B4551 Bromsgrove Road. All four orders were made in the county’s 18 November notice. The other made orders carry these diversions: Shaw Lane and Stoke Road via the A38 Worcester Road and Redditch Road; Winwood Heath Road via Shut Mill Lane, Woodfield Lane and Farley Lane.

The motorway is clear at Bromsgrove itself. National Highways’ 7-day closure report, read on 22 November, runs from Friday 20 to Thursday 26 November and lists nothing on the M5 between junctions 4 and 4a or on the M42 at junctions 1 to 3. At junction 3, the Frankley and Halesowen junction most Rubery drivers use, it lists the northbound entry slip on the night starting Tuesday 24 November and the southbound exit slip on the night starting Wednesday 25 November, both 21:00 to 06:00, under a maintenance scheme covering junctions 1 to 3. The standing order for the M5 junction 4a to M42 junction 3 drainage scheme, made on 7 August for overnight closures from 21:00 to 06:00 for about six months from 10 August, still allows closures there, with main-carriageway traffic sent via the A38, the A448, the A441, the A4023 and the A435.

Houndsfield Lane in Hollywood is the long one, and it has been shut since 16 November. Cadent’s closure, from the Alcester Road junction to Hollywood Lane, is 24 hours a day for an anticipated 75 days from 16 November, which would run to about the end of January. The diversion is via Alcester Road, Shawhurst Lane and Hollywood Lane.

No parking at any time is coming to the lanes around Beacon Hill and the Lickey Hills from Thursday 26 November. The county made an experimental order on 5 November covering parts of Monument Lane, Beacon Hill, Old Birmingham Road, Twatling Road and Warren Lane, according to its 18 November notice. It can stay for up to 18 months, and objections to it becoming permanent can be sent to the county by 5 May 2027.

What is advertised from 30 November

Apart from the third phase of Cadent’s Romsley job, which is part of an order already made, everything below is a proposed order or a BREP entry, so the dates can move.

Closures advertised in the Bromsgrove district from 30 November 2026
RoadFromDurationReason
A38 south of Oakalls, New Road junction to Oakalls roundabout30 November to 5 DecemberWeeknight closuresBREP scheme E, part construction of the south splitter island; Planned (permit granted)
Poplar Lane and Dark Lane, Romsley (Hillcrest Road to the B4551)30 November to 11 December24 hoursPhase 3 of Cadent's Romsley gas main
Pikes Pool Lane, Burcot (Alcester Road to B4096 Alcester Road)Between 30 November and 10 December2 daysPatching, county council
Woodfield Lane and Shut Mill Lane, Bell HeathBetween 30 November and 11 December2 daysPatching, county council
Newtown Lane, Belbroughton (Farley Lane to Gorse Green Lane)Between 30 November and 10 December2 daysPatching before surface dressing, county council
Parish Hill, Belbroughton (130m north east from Doctors Hill)30 November12 days, 24 hoursSewer connection, Keane Construction for Hoxley Homes; no emergency access
Seafield Lane, Portway (Beoley Lane to Cherry Pit Lane)30 November5 daysUtility work, Openreach
Woodland Road, Dodford (250m north from Victoria Road)2 December1 dayTree maintenance, Openreach
Chapel Lane, Alvechurch (Rowney Green Lane to Gravel Pit Lane)7 December5 daysDrainage and flood alleviation, county council
Beacon Hill, Rubery (Monument Lane to Hazel Road)Between 11 and 23 December2 daysResurfacing, county council
Heydon Road, Finstall (Alcester Road to B4184 Finstall Road)Between 11 and 24 December2 daysResurfacing, county council
A448 Stratford Road, Slideslow Farm roundabout to Fordhouse Road14 December2 nights, 20:00 to 05:00BREP scheme E duct crossings, surfacing, road markings and kerbs; no emergency access
Stoneybridge, Belbroughton (40m stretch, 87m west of Madelaine Road)16 December3 daysNew ducting, Openreach; no diversion, cul-de-sac

The A448 Stratford Road nights carry the longest diversion of the winter. The county’s proposed order of 18 November shuts the road between the Slideslow Farm roundabout on the A38 and Fordhouse Road for two nights from 14 December, 20:00 to 05:00, with no access for the emergency services. The signed route runs west out of town on the A448 through Market Street, St John Street and Kidderminster Road, then via the A450 and A456 Worcester Road and the A491 Stourbridge Road and Sandy Lane to the Lydiate Ash roundabout, and back down the A38 past Lickey End to the Eastern Bypass.

Parish Hill in Belbroughton is the long one in the earlier batch: 12 days, 24 hours a day, from 30 November, for a sewer connection. There is no access for emergency services, and the diversion goes via Doctors Hill, Dodford Road and Fairfield Road. Beacon Hill in Rubery is diverted via Monument Lane, the B4096 Rose Hill, the B4120 Lickey Road into Birmingham, Leach Heath Lane and Eachway. Heydon Road in Finstall is diverted via Alcester Road and Finstall Road.

Birmingham New Street has no trains all day on 24, 27 and 28 December for overhead line work, and West Midlands Railway trains from Bromsgrove through to Lichfield and Four Oaks do not run on those days. Trains from Birmingham to Worcester, Great Malvern and Hereford start or end at Birmingham Snow Hill instead and will not call at Barnt Green or Bromsgrove. Replacement buses run between Birmingham New Street and Longbridge, Barnt Green, Bromsgrove and Droitwich Spa, and between Longbridge or Barnt Green and Redditch. No trains run on Christmas Day and no West Midlands Railway trains on Boxing Day. Plans for 29 December to 2 January have not been published. On Sunday 3 January no trains run between Worcester and Bromsgrove all day, with buses from Worcester Shrub Hill to Bromsgrove.

The A38 scheme behind most of it

The A38 Bromsgrove Route Enhancement Programme, or BREP, is a £49.7 million rebuild of the road that carries traffic round the town. Phase 3 has been in delivery since 2025.

There are now three published finish dates and none of them is this year. The council’s frequently asked questions said “end of 2026” when we checked on 3 September; on 10 September the same page reads “the end of March 2027”. The programme page the council updated in July 2026 says some activities will continue into spring 2027. And in a letter of 4 September the Minister for Roads gave the majority of the programme as early 2027, with Oakalls Roundabout finishing in summer 2027. We have set the three side by side: what the Minister told Bromsgrove’s MP. In a Westminster Hall debate on 13 October the Minister gave Oakalls as June 2027.

BREP phase 3 covers the A38 between junction 4 of the M5 in the north and the A38 junction with the B4094 in the south. It is junction capacity work, localised widening, new crossings, bus priority and an active travel route between the railway station and the town centre. Colas is the main contractor, working with Griffiths and Journeo Passenger Systems.

A38 Bromsgrove Route Enhancement Programme, funding and spend
ItemAmount
Department for Transport£43,164,981
Worcestershire Local Enterprise Partnership£1,317,293
Developer contributions (section 106)£5,216,238
Total programme£49,698,512
Spent to mid-November 2026£38,585,204

Roughly £1 in every £10 of the programme is developer money, which is the practical link between the roadworks and the housing debate: the junctions are being enlarged partly because more homes are coming, and some of the homes are paying for it.

The council is candid about why the dates have moved. Its July update blames “further diversion works required of gas, water and electricity services due to inaccurate utility location records”, and says the timing of those sits with the utility companies rather than with the highway contractor. The next programme update was promised for October 2026 and never appeared; on 18 November the plan page says the next one is now due in January 2027. The council’s new Our plan to the finish page says phase 3 is about 75 per cent done and aims to finish by the end of spring 2027. It gives spend to mid-November 2026 as £38,585,204, up from £37,452,848 at the end of September, and says its timeline is “correct as of November 2026”. Our separate report sets out what the county says about penalties for the delay.

A38 BREP spend and revised end date Panel showing the A38 Bromsgrove Route Enhancement Programme. Total funding is £49,698,512, of which £38,585,204 had been spent by mid-November 2026, about 78 per cent. The council's frequently asked questions give an end date of the end of March 2027, while the Minister for Roads says the Oakalls Roundabout works are scheduled to finish in summer 2027. Three quarters spent, and the end date keeps moving A38 Bromsgrove Route Enhancement Programme phase 3, Worcestershire County Council figures, spend to mid-November 2026. Programme spend £38,585,204 spent to mid-November 2026 of £49,698,512 What the council says about finishing End of March 2027 stated in the BREP FAQs, 10 Sep 2026 Summer 2027 Oakalls, per the Minister for Roads, 4 Sep The council attributes the slip to gas, water and electricity diversions found through inaccurate utility records. Source: Worcestershire County Council, Our plan to the finish (BREP) and BREP FAQs. Chart by Bromsgrove News.
Chart by Bromsgrove News

What BREP is advertising next

We read the BREP works table again on 22 November and the county has rewritten it since 18 November. The main changes:

  • the Aldi exit weekend nights of 21 to 23 November are now described as a CCTV condition survey on a Severn Trent main, and the news page above the table gives them firm times
  • a new 27 to 30 November weekend, day and night, has been added for trial holes on the same main, with 15 to 18 January 2027 as contingency dates
  • the A38 south of Oakalls nights of 30 November to 5 December have gone from “Proposed/TBC” to “Planned”
  • a Regents Park Road weekend full closure has been added for 5 to 7 December, alongside the New Road closure
  • Scheme F at the A38 Birmingham Road junction now has dates: the weekends of 8 to 11 January 2027, with 15 to 18 January as contingency
  • new rows run the resurfacing and signal work on the Eastern Bypass and New Road to 3 February 2027

“Planned” means “traffic management permit granted”. Everything else is “Proposed/TBC”, which the county says depends on enabling works, permits, weather and third parties. The Charford Road weeknight row still reads “19 November December 2026”, as it has for a week.

A38 BREP upcoming works, as published by Worcestershire County Council and read on 22 November 2026
LocationSchemeDatesClosure type and status
A38 Stoke Road, Aldi exit to the southB21 to 23 NovemberWeekend night closures, CCTV condition survey on a Severn Trent main. Planned; times confirmed on the news page
A38 Stoke Road, Aldi exit to the southB and C27 to 30 NovemberWeekend day and night closures, trial holes on the Severn Trent main, saw cutting, duct crossings for signals and lighting. Proposed/TBC
A38 south of Oakalls, New Road junction to Oakalls roundaboutE30 November to 5 DecemberWeeknight closures, part construction of the south splitter island and extension of phase 1F. Planned
New Road, west of the A38 junctionD5 to 7 DecemberWeekend 24-hour full closure, duct crossing for the New Road signals and street lighting. Proposed/TBC
Regents Park RoadE5 to 7 DecemberWeekend full closure, duct crossing to the New Road signals and street lighting. Proposed/TBC
A38 Eastern Bypass northbound and New Road westD9 to 12 DecemberWeeknight closures, resurfacing. Proposed/TBC
Charford Road, Stoke Road junction to Lyttleton Road junctionC12 to 14 DecemberWeekend 24-hour full closures, resurfacing, duct crossings and lining. Proposed/TBC
A448 Stratford RoadE14 to 15 DecemberWeeknight closures, phase switch for splitter island works. Proposed/TBC; the county's proposed order gives two nights from 14 December, 20:00 to 05:00
A38 Eastern Bypass northbound and New Road westD16 to 19 DecemberWeeknight closures, resurfacing. Proposed/TBC
A448 Bromsgrove Highway (dual carriageway)E4 to 7 January 2027Weeknight closures, surfacing, lining and signage. Planned
A38 Birmingham Road and A38 Eastern Bypass, M42 interchange to Slideslow roundaboutF8 to 11 January 2027; 15 to 18 January as contingencyWeekend 24-hour full closures, northbound guide island removals and ducting. Proposed/TBC
Location not given by the countyB21 to 22 January 2027Weeknight closures, traffic switch onto the widened northbound carriageway. Proposed/TBC
A38 Stoke Road, Aldi exit to the southB21 to 23 January 2027Weekend night closures, contingency dates for the CCTV survey. Proposed/TBC
A38 Eastern Bypass northbound and New Road westD25 to 28 January 2027Weeknight closures, binder and surface course. Proposed/TBC
A38 Eastern Bypass, Charford Road to New RoadD29 January to 1 February 2027Weekend full closures, carriageway crossings for traffic signals. Proposed/TBC
A38 Eastern Bypass northbound and New Road westD1 to 3 February 2027Weeknight closures, high-friction surfacing. Proposed/TBC
Stoke Road, Aldi exit closedB5 to 6 February 2027Full closure, 10pm to 5am, works to the Aldi exit area. Proposed/TBC

The A448 Stratford Road nights are the only rows above covered by a county order so far, and that order is still only proposed.

The pattern to expect through the winter is the one the council has used all year: night closures between 20:00 and 06:00, weekend closures from Friday evening to Monday morning, and signed A-road diversions rather than routes through residential streets.

Sanders Park car park has reopened

Bromsgrove District Council says the extended car park reopened on the afternoon of Monday 26 October. It adds 23 standard bays, 3 disabled bays and 6 parent and child bays. Our parking page has the detail.

Parking: Stourbridge Road car park has closed

Bromsgrove District Council’s public car parks all give the first 30 minutes free, as long as you take a ticket from the machine.

Stourbridge Road car park closed permanently on 24 September, taking 71 spaces, five of them accessible. The council’s news post of 18 September gave that date, a day earlier than the 25 September in its parking order papers. The council published its notice of making on 25 September: the new Off-Street Parking Places Order came into effect that day, and anyone wanting to challenge it in the High Court has six weeks from that date. We have set out the car parks left, their prices and where season tickets still work.

Season tickets are now valid at four car parks only:

  • School Drive
  • Parkside
  • North Bromsgrove
  • New Road
Bromsgrove District Council car park charges, 08:00 to 18:00 every day including bank holidays
Car parkSpaces (accessible)1 hour3 hoursAll day
Recreation Road South292 (20)£1.00£3.00£11.00 (10 hrs)
North Bromsgrove185 (10)£1.00£3.00£6.00 (10 hrs)
School Drive128 (10)£1.00£3.00£6.00 (10 hrs)
Parkside94 (6)£1.00£3.00£6.00 (10 hrs)
St John Street82 (4)£1.30£3.803-hour maximum
Windsor Street65 (6)£1.30£3.803-hour maximum
New Road58 (4)£1.00£3.00£6.00 (10 hrs)
Aston FieldsNot statedFree for 3 hours, all day with a permit

The tariffs at the remaining car parks are unchanged by the new order.

Two other things stand out. Recreation Road South is nearly twice the price of the others for a long stay, £11 against £6, despite being the biggest car park in the town. And St John Street and Windsor Street are the two 3-hour car parks, priced higher per hour precisely because they are meant to turn over. Blue Badge holders park free everywhere, though in the two 3-hour car parks that free parking is itself capped at three hours.

Bromsgrove has no park and ride site. The station car park is the nearest thing to one: 350 spaces on New Road at £3 a day, run by Excel Parking rather than the council, and covered on our Bromsgrove train times page.

The routes that carry the town

  • The A38 is the spine. It runs from junction 4 of the M5 at Bromsgrove’s northern edge, past Catshill and along the eastern side of the town through the Slideslow, Oakalls, Buntsford Drive and Sherwood Road junctions, and on south towards Droitwich. Almost every BREP closure is on it or on a road feeding it.
  • The M5 at junction 4 is the town’s main motorway access. The M42 joins the M5 immediately north of it at junction 4a, which is why so much cross-region traffic funnels past Bromsgrove rather than round it, and why the junction 4a drainage works matter here.
  • The A448 links Bromsgrove east to Redditch and west to Kidderminster. The Bromsgrove Highway stretch between the Oakalls roundabout and the Foxlydiate junction has had repeated overnight closures under BREP scheme E.
  • The A491 runs north west towards Hagley and Stourbridge, the way most of the district’s western villages reach the town.
  • Local roads to watch during closures: Stoke Road, Sherwood Road, New Road, Regents Park Road, Churchfields and Buntsford Drive have all carried closures or multi-way lights this year.

What it means for you

  • If you use the A38 Stoke Road past Aldi, it shuts between Charford Road and the Austin Road roundabout from 8pm tonight, Sunday 22 November, to 6am on Monday. A continuous closure from 8pm on Friday 27 November to 6am on Monday 30 November is provisional.
  • If you are planning around the A38 south of Oakalls, its weeknight closures run from 30 November to 5 December, now with the permit granted.
  • If you drive near Headley Heath, Primrose Hill has been shut by flooding since 17 November.
  • If you use Old Burcott Lane at Burcot, it has been shut by a landslip since 27 October and the county gives no reopening date.
  • If you live in Rubery, Whetty Lane shuts for a day on Monday 23 November, and Beacon Hill for two days in mid-December.
  • If you park on the lanes by the Lickey Hills, no waiting at any time starts on parts of Monument Lane, Beacon Hill, Old Birmingham Road, Twatling Road and Warren Lane on Thursday 26 November.
  • If you use the M5 at junctions 4 and 4a, National Highways lists no closures there up to Thursday 26 November; junction 3 loses a slip road on the nights of 24 and 25 November.
  • If you live in Romsley near Dark Lane, Hillcrest Road or Poplar Lane, Cadent’s gas main job runs in phases to 18 December.
  • If you live in Hollywood, Houndsfield Lane has been shut 24 hours a day since 16 November, for about 75 days; the order is made.
  • If you use the A448 Stratford Road, two night closures are proposed from 14 December, with a diversion via Hagley and Lydiate Ash.
  • If you used to park at Stourbridge Road, it closed on 24 September. Season tickets now work at four car parks.
  • Anything above marked proposed or provisional can move. Check the county’s notice before you build a journey around it.

Frequently asked questions

Is the M5 closed at Bromsgrove this week?

Not at junctions 4 and 4a. National Highways’ 7-day closure report, running from Friday 20 to Thursday 26 November, lists nothing on the M5 between junctions 4 and 4a or on the M42 at junctions 1 to 3. At junction 3, the northbound entry slip shuts on the night starting Tuesday 24 November and the southbound exit slip on the night starting Wednesday 25 November, both 21:00 to 06:00.

Has Old Birmingham Road at Marlbrook reopened?

We cannot confirm it. The closure order gave an anticipated duration of 105 days from 21 July 2026, which ran to about 3 November, and the county publishes no reopening notice. Cadent is replacing a gas main, and the order allows up to 18 months if the work overruns.

When are the next A38 night closures in Bromsgrove?

The A38 Stoke Road, between the Charford Road junction and the Austin Road roundabout, shuts from 8pm on Sunday 22 November to 6am on Monday 23 November, confirmed on the county’s BREP page. A continuous closure of the same stretch from 8pm on Friday 27 November to 6am on Monday 30 November is provisional. Weeknight closures on the A38 south of Oakalls follow from 30 November to 5 December, marked planned, then a 24-hour New Road and Regents Park Road weekend on 5 to 7 December, still proposed.

When will the Bromsgrove A38 roadworks finish?

The council’s FAQ page says the end of March 2027, and its plan page aims for the end of spring 2027. The Minister for Roads told MPs on 13 October that Oakalls Roundabout was due in June 2027 on the contractor’s latest plans. The council promised a programme update in October 2026 that never appeared; the plan page now says the next one is due in January 2027.

Why is the A38 work taking so long?

The council’s stated reason is utility diversions. Gas, water and electricity apparatus has repeatedly turned up in places the records did not show, which stops work while the utility companies deal with it. In a letter to the town’s MP on 14 August the cabinet member for highways named Cadent gas apparatus as the principal factor.

How much is the A38 Bromsgrove scheme costing?

£49,698,512 in total. The Department for Transport is putting in £43,164,981, developers £5,216,238 through section 106 agreements, and the Worcestershire Local Enterprise Partnership £1,317,293. By mid-November 2026, £38,585,204 had been spent, according to the council’s plan to the finish page.

Where can I park free in Bromsgrove?

The first 30 minutes is free in every public council car park if you take a ticket. Aston Fields is free for up to three hours, and the Alvechurch, Aston Road and Sanders Park car parks carry no charges at all. Blue Badge holders park free in all of them, with a three-hour cap at St John Street and Windsor Street.

Sources

Last checked 18 November 2026. Closure dates move. Check the county council’s notice or the BREP page before you plan a journey around any of these, particularly anything marked proposed or to be confirmed.